CADOGAN

Noisy work schedule – w/c 16 January 2017

1 Sloane Gardens

Works to 1 Sloane Gardens will essentially involve work to break the tarmac outside the site on Holbein Place with two TE1000 breakers (i.e. jack hammers) from Monday to Friday.

In addition we are expecting a piling rig to arrive on site on Wednesday, after which piling works will take place on Holbein Place from Wednesday to Friday. Please note that we expect this activity to generate a high level of noise.

Cadogan requires contractors to limit this type of noisy high impact work to four hours a day, so please be assured that this should not take place out the hours of 10:00 – 12:00 and 14:00 – 16:00 during weekdays. No works are planned for Saturday or Sunday.

A detailed breakdown of scheduled works is included below.

 

32 Sloane Gardens

Works this week on 32 Sloane Gardens will primarily involve works to the basement level which we envisage may result in low noise impact.

A detailed breakdown of scheduled works is included below.

 

39/41 Sloane Gardens

Go back