CADOGAN

Noisy work schedule – w/c 30 January 2017

1 Sloane Gardens

Work will continue to take place at three different areas of the site. The breaking of the basement slab and pile probing will continue internally using two TE1000 breakers (i.e. jack hammers).

The breaking of tarmac outside the site on Holbein Place will continue all week and piling works here will re-commence on Tuesday. Additionally, excavation at 1 Sloane Gardens to expose party wall footings will take place and involve a further two jack hammers. The team will also be painting their welfare offices and site offices during the week.

Cadogan requires contractors to limit this type of noisy high impact work to four hours a day, so please be assured that this should not take place out the hours of 10:00 – 12:00 and 14:00 – 16:00 during weekdays. No works are planned for Saturday or Sunday.

A detailed breakdown of scheduled works is included below.

 

32 Sloane Gardens

We do not anticipate any noisy works taking place this week.

 

39/41 Sloane Gardens

During this week works will continue to erect scaffolding to the front and rear of the property. We will also be erecting the hoarding. We envisage that this will cause a high level of noise disruption as drilling and hammering will be taking place.

Go back
Next