Noisy work schedule – w/c 13 February 2017

1 Sloane Gardens

The works this week are as follows:
– Underpinning the basement of 1 Sloane Gardens
– Breaking pile caps at Holbein Place
– Continuation of piling works at Sloane Gardens

Cadogan requires contractors to limit this type of noisy high impact work to four hours a day, so please be assured that this should not take place out the hours of 10:00 – 12:00 and 14:00 – 16:00 during weekdays. No works are planned for Saturday or Sunday.

A detailed breakdown of scheduled works is included below.

 

32 Sloane Gardens
We do not anticipate any noisy works taking place this week.

 

39/41 Sloane Gardens
Throughout this week we will be continuing to erect scaffolding and hoarding. We will also start the setup of internal demolition work and works to the roof.
We envisage that this will cause a high level of noise disruption as drilling and hammering will be taking place and the work will also include us of a breaker.