The works this week are as follows:
– Underpinning the basement of 1 Sloane Gardens
– Breaking pile caps at Holbein Place
– Continuation of piling works at Sloane Gardens

Cadogan requires contractors to limit this type of noisy high impact work to four hours a day, so please be assured that this should not take place out the hours of 10:00 – 12:00 and 14:00 – 16:00 during weekdays. No works are planned for Saturday or Sunday.

A detailed breakdown of scheduled works is included below.

 

11 Sloane Gardens

This week work will additionally be taking place at McLaren’s site office at 11 Sloane Gardens. On Monday 20 February the GF wall will be removed to create a reception area. This will be slightly noisy.

During the week there will be a mock-up ceiling demolition and fit-out works to the meeting room.

 

32 Sloane Gardens

We do not anticipate any noisy works taking place this week.

 

39/41 Sloane Gardens

This week we will be finishing works to the external hoarding. We will also continue with the demolition work and works to the roof.

We envisage that this will cause a high level of noise disruption as drilling and hammering will be taking place and the work will also include use of a breaker.