CADOGAN

Noisy work schedule – w/c 20 March

1 Sloane Gardens

The works this week are as follows:
– Underpinning to the basement of 1 Sloane Gardens
– Breaking pile caps and constructing crane base to Sloane Gardens light well
– Steel erection to Holbein Place

Please note a crane will be moved on to site next weekend so there will be a temporary road closure on Sloane Gardens on Sunday 26th March, but pedestrian access will be maintained throughout and parking will still be available Saturday 25th March.

Cadogan requires contractors to limit this type of noisy high impact work to four hours a day, so please be assured that this should not take place out the hours of 10:00 – 12:00 and 14:00 – 16:00 during weekdays. No works are planned for Saturday or Sunday.

A detailed breakdown of scheduled works is included below.

 

32 Sloane Gardens

We do not anticipate any noisy works taking place this week.

 

39-41 Sloane Gardens

This week we will be working on basement digging and continuing with the demolition work and works to the roof. There will also be skip loading taking place.

We envisage that this will cause a high level of noise disruption as drilling and hammering will be taking place and the work will also include use of a breaker.