CADOGAN

Noisy work schedule – w/c 10 April

1 Sloane Gardens

The works this week are as follows:
– Underpinning to the basement of 1 Sloane Gardens
– Breaking pile caps to Sloane Gardens (note footpath closure)
– Steel and scaffold erection to Sloane Gardens and Holbein Place using the tower crane
– Moving the conveyor belt to Holbein Place (Ladbrokes side). A grab lorry will be located outside on the road but this will not block the shops or passing traffic

Cadogan requires contractors to limit this type of noisy high impact work to four hours a day, so please be assured that this should not take place out the hours of 10:00 – 12:00 and 14:00 – 16:00 during weekdays. No works are planned for Saturday or Sunday.

A detailed breakdown of scheduled works is included below.

 

32 Sloane Gardens

We do not anticipate any noisy works taking place this week.

 

39-41 Sloane Gardens

This week we will be working on basement digging and continuing with the demolition work and works to the roof. There will also be skip loading taking place and scabbling within the vaults to remove render.

We envisage that this will cause a high level of noise disruption as drilling and hammering will be taking place and the work will also include use of a breaker.

Go back
Next